Construction Update February 2022
8:23PM February 10, 2022
Construction
Updates by Zone
In-Service Zones: Construction including drops is complete for Brooklyn 102, Brooklyn 104, Brooklyn 105, Cope 101, Cope 102, Cope 104, Drop Zone 1, East Madison 103, East Madison 104, Heartland 104, Martinsville SE, Needmore 102, Needmore 103, Needmore 104, Paragon 101, Park Ave 101, Park Ave 104, Princes Lakes 103, Princes Lakes 104, Princes Lakes 101, Rodeo, Stadar 104, and Bean Blossom 101, Bean Blossom 102 (except for a few smaller areas awaiting permits/licenses), and Ellettsville South. New orders for these zones are continually coming in. Our target is to provide service to any new orders in these zones within 6 weeks of registering if weather allows.
Please see below for estimated timelines related to zones being constructed in 2022.
Please remember that there are many factors that could change these timelines!
Brummetts Creek 103: Aerial
construction is complete, underground construction and splicing is expected to
be completed by the end of March. Drops
and activations are expected to start in the beginning of the second quarter of
2022.
Brummetts Creek 104: Aerial
construction is complete, underground construction and splicing is expected to
be completed by the end of March. Drops
and activations are expected to start in the beginning of the second quarter of
2022.
Brummetts Creek 105: Construction
is well underway, drops and activations are expected to start in the first
quarter of 2022 and continue throughout the first half of 2022.
Carp 101: The aerial construction is complete, and
the underground construction is expected to be completed by the end of
March. Drops are expected to start shortly
after.
Carp 102: Distribution construction is in progress
and is expected to be completed by the end of March. Drops are expected to start shortly after.
Dolan 105: Construction is completed on all cabinets except for D and H. Drops and activations have started on all other cabinets and is expected to continue through spring of 2022. Cabinets D and H are expected to be completed in March, with drops and activations starting shortly after that.
Ellettsville 105: Construction
is complete and drops have started. Most
Members signed up for service should be getting activated in March and April.
Heartland 103:
Construction is complete and drops have started. Most Members signed up for service should be
getting activated in March and April.
Paragon 102: Splicing is nearing completion, and drops
are expected to start in April
Paragon 103: Splicing is nearing completion, and drops
are expected to start in April.
Romona 101: Distribution construction is expected to
start in the second quarter of 2022, with drops starting in mid to late 2022.
Romona 103: Distribution construction is expected to
start in the second quarter of 2022, with drops starting in mid-2022.
Romona 104: Distribution construction is expected to
start in the first quarter of 2022, with drops starting in mid-2022.
Spencer (North and South): Spencer
is a large zone. Distribution construction is about 10% complete and will
likely continue through the first half of 2022, with drops starting in mid-2022.
Wilbur 103:
Distribution construction is 95% completed, drops/activations are about
50% completed, and are expected to continue through the spring.
Smithville Partnership – McNeely: Distribution construction complete,
drops/activations have started and are expected to continue through spring.
Smithville Partnership – Sherfield: Distribution construction is complete
with acceptance testing occurring in February.
Drops and activations are expected to start in April of 2022.
Smithville Partnership – Modesto: Engineering is nearing completion, construction
is expected to begin in the second quarter with drops starting in the fall.
Smithville Partnership – Franklin: Construction is completed, splicing is
underway. Drops are expected to start towards the end of April.