Construction Update February 2022
8:23PM February 10, 2022
Construction
Updates by Zone
In-Service Zones: Construction including drops is complete for Brooklyn 102, Brooklyn 104, Brooklyn 105, Cope 101, Cope 102, Cope 104, Drop Zone 1, East Madison 103, East Madison 104, Heartland 104, Martinsville SE, Needmore 102, Needmore 103, Needmore 104, Paragon 101, Park Ave 101, Park Ave 104, Princes Lakes 103, Princes Lakes 104, Princes Lakes 101, Rodeo, Stadar 104, and Bean Blossom 101, Bean Blossom 102 (except for a few smaller areas awaiting permits/licenses), and Ellettsville South. New orders for these zones are continually coming in. Our target is to provide service to any new orders in these zones within 6 weeks of registering if weather allows.
Please see below for estimated timelines related to zones being constructed in 2022.
Please remember that there are many factors that could change these timelines!
Brummetts Creek 103: Aerial
construction is complete, underground construction and splicing is expected to
be completed by the end of March. Drops
and activations are expected to start in the beginning of the second quarter of
2022.
Brummetts Creek 104: Aerial
construction is complete, underground construction and splicing is expected to
be completed by the end of March. Drops
and activations are expected to start in the beginning of the second quarter of
2022.
Brummetts Creek 105: Construction
is well underway, drops and activations are expected to start in the first
quarter of 2022 and continue throughout the first half of 2022.
Carp 101: The aerial construction is complete, and
the underground construction is expected to be completed by the end of
March. Drops are expected to start shortly
after.
Carp 102: Distribution construction is in progress
and is expected to be completed by the end of March. Drops are expected to start shortly after.
Dolan 105: Construction is completed on all cabinets except for D and H. Drops and activations have started on all other cabinets and is expected to continue through spring of 2022. Cabinets D and H are expected to be completed in March, with drops and activations starting shortly after that.