Construction Update February 2022

8:23PM February 10, 2022

Construction Updates by Zone

 

In-Service Zones:  Construction including drops is complete for Brooklyn 102, Brooklyn 104, Brooklyn 105, Cope 101, Cope 102, Cope 104, Drop Zone 1, East Madison 103, East Madison 104, Heartland 104, Martinsville SE, Needmore 102, Needmore 103, Needmore 104, Paragon 101, Park Ave 101, Park Ave 104, Princes Lakes 103, Princes Lakes 104, Princes Lakes 101, Rodeo, Stadar 104, and Bean Blossom 101, Bean Blossom 102 (except for a few smaller areas awaiting permits/licenses), and Ellettsville South.  New orders for these zones are continually coming in.  Our target is to provide service to any new orders in these zones within 6 weeks of registering if weather allows. 



Please see below for estimated timelines related to zones being constructed in 2022. 
Please remember that there are many factors that could change these timelines!

  

Brummetts Creek 103:  Aerial construction is complete, underground construction and splicing is expected to be completed by the end of March.  Drops and activations are expected to start in the beginning of the second quarter of 2022.

 

Brummetts Creek 104:  Aerial construction is complete, underground construction and splicing is expected to be completed by the end of March.  Drops and activations are expected to start in the beginning of the second quarter of 2022.

 

Brummetts Creek 105:  Construction is well underway, drops and activations are expected to start in the first quarter of 2022 and continue throughout the first half of 2022.

 

Carp 101:  The aerial construction is complete, and the underground construction is expected to be completed by the end of March.  Drops are expected to start shortly after.

 

Carp 102:  Distribution construction is in progress and is expected to be completed by the end of March.  Drops are expected to start shortly after.

 

Dolan 105:  Construction is completed on all cabinets except for D and H.  Drops and activations have started on all other cabinets and is expected to continue through spring of 2022.  Cabinets D and H are expected to be completed in March, with drops and activations starting shortly after that.

 

 

 

Ellettsville 105:  Construction is complete and drops have started.  Most Members signed up for service should be getting activated in March and April.

 

Heartland 103:  Construction is complete and drops have started.  Most Members signed up for service should be getting activated in March and April.

 

Paragon 102:  Splicing is nearing completion, and drops are expected to start in April

 

Paragon 103:  Splicing is nearing completion, and drops are expected to start in April.

 

Romona 101:  Distribution construction is expected to start in the second quarter of 2022, with drops starting in mid to late 2022.

 

Romona 103:  Distribution construction is expected to start in the second quarter of 2022, with drops starting in mid-2022.

 

Romona 104:  Distribution construction is expected to start in the first quarter of 2022, with drops starting in mid-2022.

 

Spencer (North and South):  Spencer is a large zone. Distribution construction is about 10% complete and will likely continue through the first half of 2022, with drops starting in mid-2022.

 

Wilbur 103:  Distribution construction is 95% completed, drops/activations are about 50% completed, and are expected to continue through the spring.

 

Smithville Partnership – McNeely:  Distribution construction complete, drops/activations have started and are expected to continue through spring.

 

Smithville Partnership – Sherfield:  Distribution construction is complete with acceptance testing occurring in February.  Drops and activations are expected to start in April of 2022.

 

Smithville Partnership – Modesto:  Engineering is nearing completion, construction is expected to begin in the second quarter with drops starting in the fall.

Smithville Partnership – Franklin:  Construction is completed, splicing is underway.  Drops are expected to start towards the end of April. 


Backbone:   We continue to construct backbone fiber throughout our system ahead of the distribution fiber.  The backbone is used to interconnect our substations enabling smart grid technology to improve the safety and reliability of our electric distribution system. In addition, it provides the fiber connectivity from our headend to your home.  Construction is currently focusing on building backbone along the southern and northern portions of our system to create “rings.”  These rings provide redundant paths from the substations back to our headend.  This means that if one path, for some reason, gets cut, the system will automatically redirect traffic to the backup path and prevent a service outage to our electric distribution devices as well as your home.