Construction Update February 2023
1:20PM February 07, 2023
Construction
Updates by Zone
Please see below for estimated timelines related to zones being constructed in 2023. Please remember that there are many factors that could change these timelines!
In Service Zones:
Construction, including drops is complete for:
*Bean Blossom 101 & 102 *Brooklyn 102, 104, & 105 *Brummetts Creek 103, 104, & 105 *Carp 101 & 102 *Cope 101, 102, & 104 *Dolan 105 *East Madison 103 & 104 *Ellettsville 101 & 105 | Heartland 103 & 104 *Martinsville SE Needmore 102, 103, & 104 Paragon 101, 102, 103 Park Ave 101 & 104 *Princes Lake 101, 103, & 104 Stader 104 Wilbur 103 | Smithville – Rodeo |
*Indicates areas where we are awaiting equipment delivery and installation, as a result, timelines may be affected.
New orders
for these zones are continually coming in. Our target is to provide service to any new
orders in these zones within 8-12 weeks of registering if weather allows.
Active Drops Construction:
The following areas are actively building drops:
*Romona 101, 103, & 104
Construction
– In Progress:
*Spencer 101 (formerly North and South):
·
The
recent changes in zone boundaries and naming better reflect where SCI Fiber is
currently in construction and areas we plan to serve.
·
Distribution construction is nearing completion, with
drops beginning in March 2023.
Hart Lake: Distribution
construction is almost complete. Drops should
begin by April 2023.
Cunot 104: Distribution construction nearing
completion. Drops and activations
expected to begin in March 2023.
Mooresville 101: Construction has begun. Awaiting a permit from INDOT to cross SR67 as well as a pole contact permit from Hoosier Energy.
Freedom: Construction
of the backbone from our territory boundary into UDWI territory is complete. Distribution
construction has begun in the area shown in red and will continue into late
winter/early spring 2023. Expect drops
to begin in spring 2023.
Backbone: We
continue to construct backbone fiber throughout our system ahead of the
distribution fiber. The backbone is used to interconnect our substations
enabling smart grid technology to improve the safety and reliability of our
electric distribution system. In addition, it provides the fiber connectivity
from our headend to your home. Construction is currently focusing on
building backbone along the southern and northern portions of our system to
create “rings.” These rings provide redundant paths from the substations
back to our headend. This means that if one path, for some reason, gets
cut, the system will automatically redirect traffic to the backup path and
prevent a service outage to our electric distribution devices as well as your
home.
Construction of our backbone tie through Spencer will be completed by mid-February. Networking will turn up this last portion of our backbone soon after its completion.
Smithville
Partnership
Stinesville North: Distribution construction is 95% complete. Three sections are complete plus another
finishing up construction. Drops and activations in accepted areas are expected
to start in late March 2023.
Modesto: Distribution
construction is 90% complete. Drops and
activations are expected to begin in April 2023.
Indian Hills: Distribution construction in progress and
expect to be completed in March 2023. Acceptance
process will follow construction completion. Drops and activations expected in June/July
2023.
Wayne:
Distribution construction has begun, but in early
stages. Drops not expected to begin
until late summer 2023.