Construction Update January 2024
8:49PM January 04, 2024
Construction Updates by Zone
In Service Zones: Construction and drops are complete for the following zones:
Bean Blossom 101 & 102 | Martinsville SE | Smithville – Rodeo |
Brooklyn 102, 104, & 105 | Needmore 102, 103, & 104 | Smithville – Ellettsville South |
Brummetts Creek 103, 104, & 105 | Paragon 101, 102, 103 | Smithville – McNeely |
Carp 101 & 102 | Park Ave 101 & 104 | Smithville – Franklin |
Cope 101, 102, & 104 | Princes Lake 101, 103, & 104 | Smithville – Sherfield |
Cunot 104 | Romona 101, 103, & 104 | Smithville – Mount Carmel |
Dolan 105 | Spencer 101 | Smithville – Stinesville North |
East Madison 103 & 104 | Stader 104 | Smithville – Modesto |
Ellettsville 101 & 105 | Wilbur 103 | Smithville – Indian Hills |
Heartland 103 & 104 | Smithville - Wayne |
***New orders for these zones are continually coming in.
Our target is to provide service to any new orders in these zones within 8-12 weeks of registering if weather allows. ***
Active Drops Construction - The following areas are actively building drops:
- Freedom NW, W, parts of NE, town of Freedom
- Hart Lake – all areas open
- Mooresville 101
- East Madison 102
- Dolan 105 – Sample Rd West – construction on most of this area is complete and is ready for drops. There are 2 addresses on Wylie that we plan to serve, but there is still electric work that needs to be done before we can build fiber to them.
- Wilbur 101 – Templin Rd and Hwy 142 are awaiting splicing.
- Heartland 102 – on hold.
Freedom: Backbone construction from Spencer to the Freedom ODC is complete and the ODC is also online. The picture below outlines the different cabinet areas in Freedom. Freedom NW and West are actively building drops. Construction in the town of Freedom, located in the Freedom Central section, and in portions of Freedom NE are complete. These areas are being targeted because we are on a state funding timeline. Freedom NE & S – Construction nearing completion. One section along Dunn Rd in NE is waiting for make-ready by UDWI. Freedom E – Construction is in progress.
Smithville Partnership
- Devore: Finishing splicing. Drops are anticipated to start in Jan/Feb 2024.
- Deckard Ridge: Construction in progress. Targeting construction completion in the March/April 2024 timeframe. Drops would start 30-45 days afterwards.