Construction Update June 2022
10:36PM June 08, 2022
Construction
Updates by Zone
Please
see below for estimated timelines related to zones being constructed in 2022.
Please remember that there are many factors
that could change these timelines!
In-Service Zones: Construction and drops are complete for the following zones.
|
|
|
Active Drops Construction - The following areas are actively
building drops:
Carp 101 (drops are being designed)
Brummetts Creek 103 & 104
Dolan 105
Ellettsville 105
Paragon 102 & 103
Construction – In Progress:
Brummetts Creek 105: Construction is nearing completion. Drops and activations are expected to start in June 2022 and continue throughout summer of 2022.
Carp 102: The aerial construction is complete, and the underground construction is nearing completion. Weather and rock have caused delays getting the underground completed. Splicing should finish by late June. Drops are expected to start once splicing is completed.
Romona 101: Distribution construction is expected to
start in June/July 2022, with drops starting in fall 2022.
Romona 103: Distribution construction is expected to start in June/July 2022, with drops starting in fall 2022.
Romona 104: Distribution construction and splicing are almost completed. Drops should start in July.