Enter your address below to get started!

Updates

Construction Update May 2023

10:01AM May 24, 2023

Construction Updates by Zone

Please see below for estimated timelines related to zones being constructed in 2023.  Please remember that many factors could change these timelines! 


In Service Zones:

 

Construction and drops are complete for the following zones:


Bean Blossom 101 & 102
East Madison 103 & 104
Park Ave 101 & 104
Smithville – Rodeo
Brooklyn 102, 104, & 105
Ellettsville 101 & 105
Park Ave 101 & 104
Smithville – Ellettsville South
Brummetts Creek 103, 104, & 105
Heartland 103 & 104
Princes Lake 101, 103, & 104
Smithville – McNeely
Carp 101 & 102
Martinsville SE
Romona 101, 103, & 104
Smithville – Franklin
Cope 101, 102, & 104
Needmore 102, 103, & 104
Stader 104
Smithville – Sherfield
Dolan 105
Paragon 101, 102, 103
Wilbur 103
Smithville – Mount Carmel

***New orders for these zones are continually coming in. 
Our target is to provide service to any new orders in these zones within 6-8 weeks of registering if weather allows. ***


Active Drops Construction:

 

The following areas are actively building drops:


  • Spencer 101 except for Fish Creek Rd.  Distribution construction in this section is almost complete.
  • Hart Lake 103 (one section of this zone is incomplete - we are actively pursuing options to serve these members.)
  • Smithville – Stinesville North
  • Smithville – Modesto

Construction – In Progress:


Spencer 101 (formerly North and South):  All of Spencer 101 is currently under drop construction. 

 

Hart Lake: Distribution construction is almost complete. The other area of Hart Lake is a combination of feeders 101, 102, & 104.  Those are also nearing completion.

 

Cunot 104:  Construction is complete and splicing is ongoing.  We anticipate drops starting in July.

 

Mooresville 101:  Construction has begun - pending permits, construction should be completed in May.  Drops to begin in late June or July.

 

Freedom: Construction of the backbone from our territory boundary into UDWI territory is complete. Distribution construction is complete in the area shown in red and splicing is happening now.  We anticipate drops to begin in late June.  The other highlighted areas are currently under construction and will be completed in the next couple of months.